In early 2020, people in the project area of Long Thanh Airport will be allocated land in resettlement area to build houses.
On the afternoon of November 12, Dong Nai People's Committee met among departments to implement the project of land acquisition, compensation, support and resettlement of Long Thanh International Airport. This is a sub-project of Long Thanh International Airport, which has just been approved by the Prime Minister a week ago, invested by the People's Committee of Dong Nai province with a total budget of nearly 23 trillion dong.
According to Dong Nai People's Committee, the project will clear nearly 5,400 hectares of land in Long Thanh district, of which 5,000 hectares. Besides large area of Dong Nai Rubber Corporation, there will be 5,000 households with 17,000 people having to clear white. At present, two resettlement areas of Loc An - Binh Son (nearly 300 hectares) and Binh Son III resettlement area (81 hectares) are undergoing legal procedures to start construction next year.
Resettlement sites will have synchronous technical and social infrastructure. In addition to roads, green trees, water supply and drainage systems, water treatment plants, lighting, etc., there are schools, religious establishments and cultural centers to serve the new life of the people to move.
Mr. Tran Van Vinh, Vice Chairman of Dong Nai People's Committee said that the project to build the resettlement areas has been authorized by the Prime Minister for the province should be able to deploy quickly, expected in the first quarter of 2020, the household People will be handed over land to build new houses.
"In order to speed up the implementation of the project, besides the personnel of Long Thanh district, Dong Nai province will increase personnel from departments to assist in counting, measuring and assessing compensation. .. to the schedule assigned, " Vinh said.
Mr. Tran Van Vinh, Vice Chairman of Dong Nai People's Committee at the project implementation meeting on 12/11.
Relating to the land issue, leaders of Dong Nai province also directed the management agencies should pay attention to the issue of "rely slightly" on Long Thanh airport to speculate land, causing security instability local self. Especially the area of 5,000 hectares in the area of construction of the aircraft.
"Long Thanh International Airport is a national project, the relocation of compensation for site clearance for 5,000 households is not simple, therefore, departments need to deploy soon and synchronously. Where to report immediately to the Steering Committee, then can be timely in time to hand over clean premises for investors, " said Vinh.
Long Thanh international airport project, which is an airport of 4F capacity, has designed capacity of 100 million passengers and 5 million tons of cargo a year after completing three phases in the year. 2050. In which, phase I (expected to be completed in 2025), the airport will operate the runways and passenger terminals and auxiliary items ...